In 2021, Pembina Pipeline Corp. executives formed a partnership with an indigenous group to explore buying a stake or even owning the Trans Mountain Pipeline (TMX).
After years of delays and cost overruns, TMX went into service on May 1, but Canada-based Pembina is no longer as interested, executives said during its first-quarter earnings call on May 10.
“We've been pretty consistent for some time—there exists a great deal of uncertainty still on TMX,” said Cameron Goldade, Pembina senior vice president and CFO. “Obviously, one very important milestone has passed with the pipeline coming into service.”
The company has concerns about the future toll structure for the pipeline, currently owned by the Canadian government, which has promised to sell it.
At the end of last year, the Canadian government approved interim tolls for the system so the pipeline managers could start charging for shipping as soon as the line started up. The interim benchmark toll was set at $11.46/bbl, applied to shippers with a 15-year contract, Reuters reported.
The next toll schedule is still under negotiations.
TMX will triple the flow of Canadian crude to the Pacific coast, adding 590,000 bbl/d in capacity. The cost of the project has been estimated at CA$30.9 billion (US$22.79 billion), more than four times its original budget. Most analysts doubt the pipeline will be able to pay for itself.
RELATED
For Sale? Trans Mountain Pipeline Tentatively on the Market
“I understand that the toll resolution process is ongoing and is likely to take some time to see resolution,” Goldade said. “And from our perspective, there still exists a tremendous amount of uncertainty around that asset.”
Pembina executives said they did see some positives to TMX’s completion. The boost in oil production in Alberta, where the pipeline begins, will help Pembina’s NGL operations, said Jaret Sprott, senior vice president and COO.
“The number one significant impact to Pembina long-term … is increased egress. It will raise the price of the heavier oils here in Western Canada,” Sprott said. “That should spur on incremental supply that will require condensate.”
RELATED
Imperial Expects TMX to Tighten Differentials, Raise Heavy Crude Prices
Pembina has a large condensate business in Edmonton, Sprott said, which should see a significant benefit from more oil production to fill TMX.
The midstream executives also discussed another major project, the Cedar LNG export terminal. The proposed terminal is to be located on the West Canadian Coast, far north of the TMX terminus point near Vancouver.
Pembina announced that it secured long-term commercial agreements for the project, crucial for the development of an LNG plant.
Thanks to the agreements, executives expect to make a final investment decision on the project in June.
Recommended Reading
Technip Energies Wins Marsa LNG Contract
2024-04-22 - Technip Energies contract, which will will cover the EPC of a natural gas liquefaction train for TotalEnergies, is valued between $532 million and $1.1 billion.
Ohio Utica’s Ascent Resources Credit Rep Rises on Production, Cash Flow
2024-04-23 - Ascent Resources received a positive outlook from Fitch Ratings as the company has grown into Ohio’s No. 1 gas and No. 2 Utica oil producer, according to state data.
Chevron, Total’s Anchor Up and (Almost) Running
2024-05-07 - During the Offshore Technology Conference 2024, project managers for Chevron’s Anchor Deepwater Project discussed the progress the project has made on its journey to reach first oil by mid-2024.
Sinopec Brings West Sichuan Gas Field Onstream
2024-03-14 - The 100 Bcm sour gas onshore field, West Sichuan Gas Field, is expected to produce 2 Bcm per year.
TotalEnergies Restarts Gas Production at Tyra Hub in Danish North Sea
2024-03-22 - TotalEnergies said the Tyra hub will produce 5.7 MMcm of gas and 22,000 bbl/d of condensate.