CAMAC Energy Inc. announced that Allied Energy PLC has contracted Wellstream International Ltd. to design, engineer, and manufacture the production flowline and production riser for the completion of the Oyo #7 well offshore Nigeria.
Wellstream is scheduled to deliver the 3,495 m (11,466 ft) of 6-in production flowline and 1,105 m (3,625 ft) of 6-in production riser to the Oyo field in July 2013, where it will be used to tie the production from Oyo #7 to the FPSO unit. Allied also has an option to purchase and receive a duplicate set of materials for its follow up production well, Oyo #8, by September 2013.
Allied has also engaged the subsea engineering firm, Deep Trend Inc. to provide subsea equipment management services, working closely with Wellstream on the design of the subsea flowlines and risers. Deep Trend will also provide broader subsea system engineering support for the definition and planning of the Oyo #7 tie backs.