Petrofac is in a race against time to get commissioning operations on the FPF-1 floating production unit (FPU) completed before sailaway from the Remotowa shipyard in Poland.
The FPU is destined for Ithaca Energy’s Greater Stella Area (SEN, 32/14) development in the U.K. North Sea.
Ithaca said that at this stage in the modifications programme the “critical path” to achieving sailaway of the FPF-1 is the completion of commissioning operations, which began during the third quarter.
“Full completion of these operations while the vessel is located in the yard is key to avoiding an extended period of more complicated offshore commissioning activities and delay to the startup of production,” Ithaca said.
Continued progress is being made on close out of precommissioning activities on the vessel, enabling the various topsides processing, utilities and accommodation sub-systems to be fed into the main commissioning programme.
Commissioning of the electrical switchboards that distribute power around the vessel is nearing completion, and electrical loop testing on the process control and safety systems is progressing well, the company said.
Internal vessel inspection activities are advancing, along with commissioning of the various utilities systems.
Preparation also is underway for the startup and commissioning of the power generators in the coming weeks, which represents a key milestone in the ongoing work programme.
Following the completion of various offshore campaigns during the quarter, all the subsea infrastructure that is required to be installed prior to the arrival of the FPF-1 on location is now in place.
Recommended Reading
Oceaneering Won $200MM in Manufactured Products Contracts in Q4 2023
2024-02-05 - The revenues from Oceaneering International’s manufactured products contracts range in value from less than $10 million to greater than $100 million.
E&P Highlights: Feb. 5, 2024
2024-02-05 - Here’s a roundup of the latest E&P headlines, including an update on Enauta’s Atlanta Phase 1 project.
CNOOC’s Suizhong 36-1/Luda 5-2 Starts Production Offshore China
2024-02-05 - CNOOC plans 118 development wells in the shallow water project in the Bohai Sea — the largest secondary development and adjustment project offshore China.
TotalEnergies Starts Production at Akpo West Offshore Nigeria
2024-02-07 - Subsea tieback expected to add 14,000 bbl/d of condensate by mid-year, and up to 4 MMcm/d of gas by 2028.
US Drillers Add Oil, Gas Rigs for Third Time in Four Weeks
2024-02-09 - Despite this week's rig increase, Baker Hughes said the total count was still down 138 rigs, or 18%, below this time last year.