The state of Western Australia has ordered an inquiry into a delay in burying carbon dioxide emissions at Chevron Corp.’s (NYSE: CVX) Gorgon LNG project, which could lead to a change in conditions on the project, on May 10.
The state approved the $54 billion Gorgon project in 2009 on the condition that at least 80% of carbon dioxide released in its gas processing operations over a five-year rolling average period would be buried.
“It has become apparent there needs to be a clearly defined start point for the commencement of the five-year rolling average,” Stephen Dawson, the state environment minister, told reporters in the Perth, the state capital, on May 7, according to an email sent to Reuters by his spokeswoman.
He ordered the state’s Environmental Protection Authority to report back within the next nine months whether the conditions should be changed, along with any other recommendations.
Chevron said it welcomed the review “to clarify the existing condition” on the carbon capture project.
“Our focus is on the safe commissioning and start-up of the carbon dioxide injection project and achieving a high percentage of injection over the 40-year life of the Gorgon project,” a Chevron spokeswoman said in emailed comments.
Chevron told the government last December it would not be able to start capturing and burying carbon dioxide until the fourth-quarter of 2018 at the earliest, after having found problems with valves and pipeline equipment during commissioning of its AU$2.5 billion (US$1.9 billion) injection system.
The Gorgon carbon dioxide injection system is the world’s largest capture and storage project.
Processing operations began in March 2016, when Gorgon started producing gas from the Jansz field.
However, Chevron only intended to start burying carbon dioxide after it started producing from the Gorgon field, which has a higher carbon dioxide content. Production started there in 2017.
Gorgon LNG is owned by Chevron, ExxonMobil Corp. (NYSE: XOM), Royal Dutch Shell (NYSE: RDS.A), and Japan’s Osaka Gas, Tokyo Gas and JERA.
Recommended Reading
Exxon, Chevron Tapping Permian for Output Growth in ‘24
2024-02-02 - Exxon Mobil and Chevron plan to tap West Texas and New Mexico for oil and gas production growth in 2024, the U.S. majors reported in their latest earnings.
Mark Ross to Retire as President of Chevron Shipping Co.
2024-01-24 - Barbara Pickering will succeed Mark Ross as president of Chevron Shipping Co.
Hess Corp. Boosts Bakken Output, Drilling Ahead of Chevron Merger
2024-01-31 - Hess Corp. increased its drilling activity and output from the Bakken play of North Dakota during the fourth quarter, the E&P reported in its latest earnings.
CEO: Coterra ‘Deeply Curious’ on M&A Amid E&P Consolidation Wave
2024-02-26 - Coterra Energy has yet to get in on the large-scale M&A wave sweeping across the Lower 48—but CEO Tom Jorden said Coterra is keeping an eye on acquisition opportunities.
NGL Growth Leads Enterprise Product Partners to Strong Fourth Quarter
2024-02-02 - Enterprise Product Partners executives are still waiting to receive final federal approval to go ahead with the company’s Sea Port Terminal Project.