The subsea completion string had to provide fishability within the 9 7/8-in. tieback (limiting the connection outside diameter (OD) to 7 in.), efficient fracturing hydraulics, mechanical and pressure integrity to absolute pressures up to 29,000 psi during screenout, sustained elevated external pressures of 24,500 psi absolute during fracture stimulation with a tubing leak operations and the capability to complete multiple trips (20) while maintaining sealability.
Similar wells have been completed with up to four OD tapered strings. Tapered strings limit the treating rate during fracture stimulation and often yield a less desirable fracture network, potentially reducing production capability. To maximize
The design and qualification program included predicting loads applied to the completion string and identifying safety factors. Finite element analysis (FEA) was used to simulate loads and confirm the design. The connection was physically tested to predicted loads and physical test data correlated back to FEA-generated predictions.
Determination of loads and stresses applied to the completion string was crucial. The completion string was modeled for a series of load cases including hook load, fracture stimulation, fracture stimulation with leak, screenout during stimulation and perforation of the well. Values for axial loads, pressure loads and temperature were calculated along the depth of the completion string for these load cases.
Defining tubular specifications was straightforward. The tube had to meet load requirements, accommodate a maximum connection OD of 7 in., a minimum connection inside diameter (ID) of 4 ¼ in. and have a large tube ID to maximize hydraulic efficiency during the frac pack operation. A 5 7/8-in. OD, 0.500 in. wall, S-135 grade pipe suited all load conditions and provided the largest ID possible for minimal fluid friction loss during the frac pack.
For the connections, Grant Prideco’s eXtreme torque XT connection offered an improved thread form and reduced taper compared to the API connection design. For completion operations, the company’s metal-to-metal seal version of XT, the XT-M connection, provided a pressure-rated rotary shouldered connection (RSC). This connection, with a radial metal-to-metal flank seal on the pin nose, is gas-tight pressure rated to 15,000 psi internal pressure and 10,000 psi external pressure. A 7-in. OD and 4 ¼-in. ID configuration is standard for XT-M57 on 5 7/8-in. pipe.
The connection was evaluated for absolute pressure, a novel FEA approach. When analyzing connections with FEA, it is typical to apply only differential pressure across the connection. If internal and external pressures are high, this approach can be misleading. The application of absolute internal and external pressure, even when equal in magnitude, generates tangential and radial stress within the connection. FEA results revealed that the connection’s extended box counterbore lacked stability under the anticipated external pressure and compressive loads at the bottom of the well. The fracturing-with-leak case (4,000 psi leak) resulted in high compression (215,160 lb plus compression from makeup) and external pressure (25,279 psi), which significantly exceeded the material strength at the box counterbore. Collapse was predicted. A modification of the existing connection was necessary.
To provide additional rigidity and structural stability to the box counterbore, the counterbore length was shortened from 2 ¼ in. to 5/8 in. A series of design iterations determined the proper pin length, box depth, and gap width to balance the stresses in the box counterbore and pin nose. The metal-to-metal seal design remained unchanged.
The modified connection (CT-M57) was analyzed for anticipated
High-strength tool joint material
API tool joints have a minimum yield strength requirement of 120,000 psi. The
The material’s fracture toughness for the upper end of the strength/hardness range was critical. Fracture toughness equivalent or better than current requirements for standard tool joint material would be required. This was accomplished with special 4130 modified steel with high alloying elements, low nonmetallic impurity elements and a quenching medium that assures martensite transformation.
Testing challengesSimultaneously applying internal and external absolute pressures instead of the more common differential pressure created a challenge in physically testing the CT-M57 connection. To qualify the connection for
To further validate the design process, strain gauge data obtained during physical testing was compared to earlier FEA strain predictions. FEA prediction correlated reasonably well with the test data, especially in predicting overall trends. Physical test data did not indicate overall strain levels higher than FEA predictions and no failures or leaks were observed during the test program. The connection was accepted for use on the
The
Evolution of rotary shouldered connections has continued with the development of a new, third generation RSC design, TurboTorque. CT-M design improvements have been incorporated in this new design.
Engineering and design typically result in tradeoffs. Second generation designs such as CT-M have increased torque and hydraulic performance but with a trade-off of increased make-up time. Because of their slower tapers and shallower stab depth, second generation connections typically require 2-3 times the number turns from stab to makeup compared to API connections. TurboTorque has eliminated this tradeoff by using a proprietary double-start thread form that reduces the revolutions from stab by at least 50%. This provides a considerable savings in rig time and money.
Recommended Reading
Barnett & Beyond: Marathon, Oxy, Peers Testing Deeper Permian Zones
2024-04-29 - Marathon Oil, Occidental, Continental Resources and others are reaching under the Permian’s popular benches for new drilling locations. Analysts think there are areas of the basin where the Permian’s deeper zones can compete for capital.
CEO: Continental Adds Midland Basin Acreage, Explores Woodford, Barnett
2024-04-11 - Continental Resources is adding leases in Midland and Ector counties, Texas, as the private E&P hunts for drilling locations to explore. Continental is also testing deeper Barnett and Woodford intervals across its Permian footprint, CEO Doug Lawler said in an exclusive interview.
For Sale, Again: Oily Northern Midland’s HighPeak Energy
2024-03-08 - The E&P is looking to hitch a ride on heated, renewed Permian Basin M&A.
CNX, Appalachia Peers Defer Completions as NatGas Prices Languish
2024-04-25 - Henry Hub blues: CNX Resources and other Appalachia producers are slashing production and deferring well completions as natural gas spot prices hover near record lows.
BPX Looks to Ramp US Production Over 60% by 2030
2024-05-16 - BPX Energy is looking to boost its U.S. production over 60% by 2030 as it considers bringing online a fourth processing facility in the Permian by mid-year 2025, Clark Edwards, the company’s vice president of development, said during SUPER DUG in Fort Worth.